This inquiry, established by the NSW Department of Climate Change, Energy, the Environment and Water, was asked to investigate, report on and where thought desirable make recommendations as to allegations that Hunter Gas Pipeline Pty Ltd or related parties (Santos) have acted inconsistently with three conditions of an Authority to Survey (Authority) granted under the Pipelines Act 1967 (NSW):
• condition 4 (about reasonable level of negotiation and/or communication and providing written notice of intent to access under the powers of the Authority)
• condition 8 (about exhausting reasonable attempts to resolve disputes regarding the Authority)
• condition 12 (about the process of informing parties regarding possible compulsory acquisition).

The Investigators’ findings are detailed in this report but, in summary, regarding these three conditions:
• Santos is not ‘in breach’ of condition 4 because it has not yet sought to use the Authority powers. If, at any stage in the future, Santos does propose to use these powers, then Santos will need to demonstrate: (a) when and how it has provided the particular owner/occupier with clear information of the potential impacts of what the Authority use will involve; and (b) that owner/occupier had adequate time to engage with Santos after the provision of that information.
• Santos is not ‘in breach’ of condition 8 because there is no evidence of Santos refusing to engage with landholders seeking to raise disputes about compliance with Authority Conditions. Santos cooperated in full with this dispute resolution process initiated by the Department, and has also provided a point of contact for continued engagement with landholders who have raised concerns as part of this investigation.
• There is insufficient evidence of Santos or its agents expressly breaching Condition 12. It is a question of balance as to when the reference to Compulsory Acquisition can be made in land access negotiations, and the Investigators note that no mention of Compulsory Acquisition is also not appropriate. It is important for landholders to have complete information in entering negotiations about land access, and this extends to understanding the compulsory acquisition process, in full, and its relevance to the matters being negotiated.
Original languageEnglish
PublisherNSW Department of Climate Change, Energy, the Environment and Water
Number of pages35
Publication statusPublished - 27 Jul 2024

UN SDGs

This output contributes to the following UN Sustainable Development Goals (SDGs)

  1. SDG 13 - Climate Action
    SDG 13 Climate Action

Fingerprint

Dive into the research topics of 'Investigation into complaints concerning use of the Authority to Survey – Hunter Gas Pipeline: Report to (NSW) Department of Climate Change, Energy, the Environment and Water'. Together they form a unique fingerprint.

Cite this